22 October 2014

Class Room Building - All panels are installed

Class Room Building - Thank you for your work!

Planning:
- 23 October: Public holiday
- 24 October: Inverters to installed on the Class Room Building
- 27 October: Reception of AC materials (drawings and installation manuals are available on this blog). Don Bosco's electricians will then start the installation of the AC part. Kamworks' staff will come at the end to help on the connections.

21 October 2014

Class Room Building - The mechanical team (5 students up + 2 students down + 1 teacher) is bringing the panels up

Class Room Building - The electrical team (5 students + 2 teachers) is installing the panels and doing the cabling (strings + extension to the inverters) 

Class Room Building - The electrical team

Class Room Building - 96 panels installed today (their record!)

Class Room Building - At the end of the working day (2/3 done)

Total installed on Class Room Building:INV1 - Strings 1 and 2INV2 - Strings 1 and 2INV3 - Strings 1 and 2
INV4 - Strings 1 and 2
INV5 - Strings 1 and 2
INV6 - Strings 1 and 2
INV7 - String 1




20 October 2014

Class Room Building - Install panels (1/3 done)

Class Room Building - Install panels

Total installed on Class Room Building:
INV1 - Strings 1 and 2
INV2 - String 1
INV3 - Strings 1 and 2



17 October 2014





One panel broke during manipulation - Be very careful! 

Class Room Building - Preparation of the hoist, wooden boards. First string installed on the roof

Total installed on Class Room Building:
INV1 - String 1

14 October 2014

 Secretarial Building - Install the last panel of the roof!

Secretarial Building - The electrical team after they installed all panels of the secretarial building roof

Secretarial Building - All panels are installed and connected in strings (ready to plug to the inverters)

Note:
- 15 October 2014: No work (National Holiday - Commemoration Day King Sihanouk)
- 16 October 2014: No work (Start of the technical school year - 1st year students)

13 October 2014

Secretarial Building - Install the panels

 Secretarial Building - Extend cables and add connectors

Secretarial Building - 60 panels installed today

Total installed on Secretarial Building:
INV10 - Strings 1 and 2
INV11 - Strings 1 and 2
INV12 - Strings 1 and 2
INV13 - Strings 1 and 2
INV14 - Strings 1 and 2

11 October 2014

 Secretarial Building - Install inverters on the wall

Secretarial Building - Optimization of the structures arrangement


Note: Class Room Building - The structures are installed. We can't start to install panels on that roof because the hoist is used for the Secretarial Building. We will start the installation of panels on the Class Room Building when the installation of the Secretarial Building is finished.

10 October 2014

Class Room Building - All rails are installed and leveled

Secretarial Building - Start to install inverters on the wall

Secretarial Building - Panels installed for INV10, INV11 and string 1 of  INV12 (60 panels installed)

9 October 2014

Training for the students and teachers (electricians) on basics solar and on the panels installation. Training materials are available on this blog.

Training session n°2

Secretarial Building - Bring the inverters up

Secretarial Building - Prepare to bring the panels up

Secretarial Building - 24 panels installed (strings 1 and 2 of the inverter 10)

Class Room Building - Continue to prepare the transversal rails

8 October 2014

Secretarial Building - Straighten rails 

Secretarial Building - Straighten rails 

Secretarial Building - The hoist is ready to use

Class Room Building - Fix the longitudinal rails, Use a metal piece to straighten the rails from the beginning

Class Room Building - The longitudinal rails are all installed. The transversal rails are prepared.

Class Room Building - The team at the end of the day!


7 October 2014

Secretarial Building - The rain stopped. Let's continue to work on the mounting structures
Secretarial Building - Bring the hoist up

Secretarial Building - Bring the hoist up

Class Room Building - Longitudinal rails

Some part of the roof are broken and have to be replace

Students and teachers waiting for the rain to stop...

6 October 2014

A lot of rain today... So, we work inside!

Workshop - Preparation of the support to bring panels up

Workshop - Preparation of the hoist

Class Room Building - Add supports under the roof

3 October 2014

Secretarial Building - Continue to place the longitudinal rails

Secretarial Building - Longitudinal rails installed

Secretarial Building - Mechanical team

2 October 2014

Preparation Mounting Structures

Secretarial Building - Longitudinal rails

Secretarial Building - Longitudinal rails

Class Room Building - Longitudinal rails